Wednesday, November 18, 2015

Foundation is Finished!

It took one more weekend to finish up the foundation work.  I pulled the forms from the previous weekend, and Curtis and I backfilled the foundation with the leftover gravel and topsoil.  



Before the final foundation work could start, the rotten portion of the sill needed to be replaced.  That was step one last Saturday, and here's the final result!


Next came replacing the giant granite capstone.  It took awhile to get it lined up, tilted up, and then jacked in place, but we did it!


Here's how it looked at the end of the day Saturday:


On Sunday, Dale came back to pour the last bit of concrete and frame in the window.  Here he is placing the last brick!


As of Sunday afternoon, we finally have a fully enclosed basement!


I stripped the forms the week, and here is the final view of the wall, in all of its glory:

And here's the final inside shot:

We'll finish backfilling the hole and grading the backyard so the water can actually drain away from the house.  That's for next weekend, then the inside work can finally begin!